Petromidia Turnaround 2020

Petromidia Turnaround 2020

2020 Turnaround was the biggest Turnaround performed until now on the Petromidia Platform - 1042 Static Equipment; 173 Rotary Equipment; 3000 Pipelines; 600 Electrical Equipments; 1580 Found Works; 22 Separate projects implemented during TA period

The entire process, at EPCM level, was managed by Rominserv specialists in only 45 days, during March - April 2020 

Main figures:  

  • Around 4 000 peoples working at the same time;
  • Over 100 companies involved in TA activities;
  • Over 200 000 cubic meters of scaffold; 
  • Over  50 lifting equipments;
  • “ZERO” external contracts/resources (outside of Romania) for Management, Execution and Technical Assistance

2020 Turnaround showed the ROMINSERV ability to adapt to critical situations arising from the context created by the COVID 19  and to manage them with excellent results:

  • ZERO technical incidents;
  • ZERO accidents;
  • ZERO infected people. 
  • All of the works have been  fully completed within the agreed budget;

Galerie

Petromidia Turnaround 2020
Petromidia Turnaround 2020
Petromidia Turnaround 2020
Petromidia Turnaround 2020

Descoperă și alte proiecte

Modernizarea rafinăriei Petromidia


Află mai multe
Modernizarea rafinăriei Petromidia

Modernizarea rafinăriei Pavlodar


Află mai multe
Modernizarea rafinăriei Pavlodar

Proiecte Downstream


Află mai multe
Proiecte Downstream

Petromidia FCC


Află mai multe
Petromidia FCC

Petromidia Turnaround 2020


Află mai multe
Petromidia Turnaround 2020

New SRU


Află mai multe
New SRU

Isaccea


Află mai multe
Isaccea